| Client |
Construct Limited |
| Principle |
Robin Ratcliffe |
| Consultant |
Design Engine |
| Project Duration |
10 Days |
Project Scope |
To Drill 12 house piles up to 1500 Ø, 21m deep |
Machines Used |
Soilmec R312, Kobelco 7055 Crane, EX120 |
Challenges |
Site access for this project was particularly challenging due to a long, narrow driveway. The driveway measured 300m in length and 3.2m in width, making it a very tight fit for our machinery. Each piece of machinery was measured to the nearest mm, and trees were trimmed where necessary to allow access. Delivery trucks were required to reverse the entire length of the driveway, as there was no room to turn around on departure. Specialised house-moving trucks were used to deliver the reinforcing cages. No onsite storage was available, so materials were bought to site in stages. The project was completed successfully and on time with a TVNZ film crew recording our progress for an upcoming television programme. |
|
 |
| Client |
Arrow International |
| Principle |
Telecom |
| Consultant |
Tokin and Taylor |
| Project Duration |
4 Days |
Project Scope |
A single pile of 1500 Ø, 4m deep- inside a telecommunications tower |
Machines Used |
Hired crane, modified Vibrator Head |
Challenges |
The site had one point of access; a driveway between two buildings just 2.3m apart reducing the options for machinery. Using a very small hired crane, part of the roof was removed. The hole was dug by hand (into sandstone) and a permanent caisson was vibrated into position. With machinery access impossible, a vibrator head was removed and dismantled from one of machines, then successfully modified to suit the situation. As concrete trucks could not access the site, they were parked on the road, and the concrete was pumped down the 50m driveway. |
|
 |
| Client |
Balfour Beatty United Group Ltd |
| Principle |
W.E.L. Networks |
| Consultant |
BECA |
| Project Duration |
May - August 2010 |
Project Scope |
To carry power generated by the new Te Uku Wind Farm by Meridian Energy, an upgrade of the existing 33 kV transmission line from Te Uku to Te Kowhai substations was required.
149 pole foundation piles were constructed, ranging in depth from 3.0 m to 9.5 m, and a diameter of 1.050 m. |
Machine Required |
Komatsu PC 200 and Volvo EC140B pendulum rigs, Bulldozer and 4WD tractor with trailer and helicopter for material deliveries to remote sites. |
Challenge |
In the soft ground conditions full length permanent caissons were required. The caissons needed to be airlifted into place in sections due to the helicopter’s lifting capacity.
Some of the piles were located in areas with basalt rock present, resulting in our crew having to be prepared for all eventualities.
Our piling crew carried out the project through the heart of winter.
Specialized and/or difficult projects are where Spiral Drillers Civil Ltd excel.
If you or someone you know needs help with a piling project, please don’t hesitate to contact our professional team. |
|
 |
Project description |
Drill 900mm diameter and 1200mm diameter building piles approx. 20m deep with all piles being spiral grooved |
Machine used |
2 x Soilmec drilling rigs |
Special difficulties |
Project finished ahead of schedule and on budget |
|
 |