Piling Projects

Project Name - Puhinui Footbridge and Sheet Pile Across Rail Corridor
Client Hawkins Infrastructure
Principle Kiwi Rail and Watercare.
Consultant PETERS AND CHEUNG LIMITED
Project Duration 6 Weeks

Project Scope

Footbridge piles for railway station and water pipe crossing    the rail corridor

Machines Used

7045 Crane, 7055 with PD6000, Ape Vibro Hydraulic Hammer, Ex120 and EX40.

Challenges

The 60 metres of sheet piling which crossed the main trunk line had to be completed in less than 30 hours to allow for the 2m diameter pipe to be installed over the Christmas shutdown.
Our part started 6.00am Boxing day and needed two crews working two shifts around the clock, Three 50 Ton cranes were on site as well as three hydraulic vibratory hammers to allow for any breakdowns that could occur.

Our portion of the project was completed ahead of schedule which considering the dire weather that was encountered was a huge achievement. The crews then concentrated on the driven piles for the foot bridge, 40 piles down to 30 metres. These piles also tested our guys as the rain was relentless. The piles were installed ahead of schedule and were finished on New Year’s eve giving everyone a chance to celebrate.

 

Project Name – Ratcliffe House Piles - Hamilton
Client Construct Limited
Principle Robin Ratcliffe
Consultant

Design Engine

Project Duration

10 Days

Project Scope

 To Drill 12 house piles up to 1500 Ø, 21m deep

Machines Used

Soilmec R312, Kobelco 7055 Crane, EX120

Challenges

Site access for this project was particularly challenging due to a long, narrow driveway.  The driveway measured 300m in length and 3.2m in width, making it a very tight fit for our machinery.  Each piece of machinery was measured to the nearest mm, and trees were trimmed where necessary to allow access.  Delivery trucks were required to reverse the entire length of the driveway, as there was no room to turn around on departure.  Specialised house-moving trucks were used to deliver the reinforcing cages.  No onsite storage was available, so materials were bought to site in stages.  The project was completed successfully and on time with a TVNZ film crew recording our progress for an upcoming television programme.

Project Name – Arrow Tower – St Heilers, Auckland
Client Arrow International
Principle Telecom
Consultant

Tokin and Taylor

Project Duration

4 Days

Project Scope

 A single pile of 1500 Ø, 4m deep- inside a telecommunications tower

Machines Used

Hired crane, modified Vibrator Head

Challenges

The site had one point of access; a driveway between two buildings just 2.3m apart reducing the options for machinery.  Using a very small hired crane, part of the roof was removed.  The hole was dug by hand (into sandstone) and a permanent caisson was vibrated into position.  With machinery access impossible, a vibrator head was removed and dismantled from one of machines, then successfully modified to suit the situation.  As concrete trucks could not access the site, they were parked on the road, and the concrete was pumped down the 50m driveway.

Project Name - Western Network Line Upgrade - Raglan
Client Balfour Beatty United Group Ltd
Principle W.E.L. Networks
Consultant BECA
Project Duration May - August 2010

Project Scope

To carry power generated by the new Te Uku Wind Farm by Meridian Energy, an upgrade of the existing 33 kV transmission line from Te Uku to Te Kowhai substations was required.
149 pole foundation piles were constructed, ranging in depth from 3.0 m to 9.5 m, and a diameter of 1.050 m.  

Machine Required

Komatsu PC 200 and Volvo EC140B pendulum rigs, Bulldozer and 4WD tractor with trailer and helicopter for material deliveries to remote sites.

Challenge

In the soft ground conditions full length permanent caissons were required.  The caissons  needed to be airlifted into place in sections due to the helicopter’s lifting capacity.

Some of the piles were located in areas with basalt rock present, resulting in our crew having to be prepared for all eventualities.
Our piling crew carried out the project through the heart of winter.
Specialized and/or difficult projects are where Spiral Drillers Civil Ltd excel.

If you or someone you know needs help with a piling project, please don’t hesitate to contact our professional team.
Project Name - University of Auckland Engineering School

Project description

Drill 900mm diameter and 1200mm diameter building piles approx. 20m deep with all piles being spiral grooved

Machine used

2 x Soilmec drilling rigs

Special difficulties

Project finished ahead of schedule and on budget

Project Name - Grower's Stadium, Pukekohe - Light Foundations

Project description

Construct 1500mm diameter x 10m deep piles for light towers

Machine used

Soilmec R312

Special difficulties

As this is a rugby stadium, no damage could be caused to the grounds.  Project completed on schedule

Project Name - Rydges Hotel, Auckland

Project description

Construct 17 piles ranging from 450mm diameter to 750mm diameter up to 20m deep with all piles being spiral grooved

Machine used

Soilmec CM39 and pendulum machines

Special difficulties

Traffic management and pedestrian access required.  Restricted site area to work in

Project Name - Rydges Hotel, Auckland

Project description

Drill 5 x 450mm diameter x 16m deep micro piles to underpin and strengthen existing foundations

Machine used

MTrack

Special difficulties

A challenging project as drill heads had to be altered to penetrate through rock and there was limited head height

Project Name - Queenstown Road access shaft

Project description

Drill 2.4m dia x 10m deep shaft to retrieve a locked drilling head

Machine used

Soilmec R312

Special difficulties

Traffic management required and a restricted site area to work in

Project Name - 1 Hobson Street, Auckland

Project description

Construct pile foundations for high rise building with underground carpark

Machine used

Soilmec CM39

Special difficulties

Penetration through existing seawall required

Project Name - Warwick Street, Westmere

Project description

Drill 12 x 450mm diameter x 6.5m deep house piles for basement

Machine used

MTrack

Special difficulties

Limited headroom

Project Name - Hepburn Substation, Auckland

Project description

Drill 1500mm diameter x 4m deep pole foundation for wires feeding into substation

Machine used

Volvo 14T

Special difficulties

Overhead power wires

Project Name - Vodafone Tower, Pt Chevalier

Project description

Construct cast in-situ pile foundations 900mm diameter x 15m deep for Vodaphone tower

Machine used

Soilmec CM39

Special difficulties

Site had to be kept clean at all times due to close proximity to road

Project Name - Blockhouse Bay

Project description

Install five (5) screw piles with adjusting corbel heads to support footings

Machine used

EX120

Special difficulties

House was sinking

Project Name - Screw Piles, Wiri

Project description

Install cluster of four screw piles under pad foundation to support abutment for a new pipe bridge

Machine used

MTrack

Project Name - Timber Retaining Wall, Howick

Project description

Retain along boundary of property, excavate driveway and construct further retaining wall for new right of way

Machine used

EX40

Special difficulties

Creating right of way for new subdivision behind existing house

Project Name - Drake Street, Auckland

Project description

Soldier pile retaining wall on boundary of construction site, topdown construction used to create basement for new high rise building

Machine used

Soilmec CM39 & Volvo 14T

Special difficulties

Restricted access, limited workspace, drilling against existing buildings and restricted work hours due to residential properties in the vicinity.  Old water wells on property had to be cased and cleaned out to enable location of new piles

Project Name - Waimauku Village, Auckland

Project description

Drilled and placed poles with concrete, drove poles, and installed tiebacks to deadman to strengthen 100m long x 3.5m high timber retaining wall

Machine used

PD1200 & PC200

Special difficulties

Working in conjunction with earthmoving contractor constructing new retaining wall for village shops.  Limited timeframe for completion of project

Project Name - New World, Remuera

Project description

Drill and constructed 20 piles for refurbishment of supermarket

Machine used

Yanmar 1.5T

Special difficulties

Confined space, work had to be carried out through the night before opening the next day and aisles had to be kept clean

Project Name - Ranfurly Street, Epsom

Project description

Drill 600mm dia x 7m deep soak hole behind house

Machine used

EX40

Special difficulties

Difficult access

Project Name - Hobsonville, Auckland

Project description

Abutment retaining piles for new bridge

Machine used

Mercedes Unimog

Project Name - Access shaft, Orakei, Auckland

Project description

Drill 2.6mm diameter x 15m deep access shaft and install caisson onto sewer line

Machine used

Soilmec R312

Project Name - Bridge Widening Abutments, Glenbrook

Project description

Pile drive steel universal columns for bridge widening abutments.  Piles were spliced and driven to achieve design loading

Machine used

PD1200

Special difficulties

Environmental issues – no contamination of stream

Project Name - Herne Bay

Project description

Drill 73 x 450mm to 600mm diameter x 9m deep piles along boundary line for excavation of new basement for house

Machine used

Volvo 14T

Project Name - Great South Road, Penrose

Project description

Drill 600mm diameter sign foundation into solid basalt rock

Machine used

Soilmec R312

Special difficulties

Traffic management required as working on roadway

Project Name - Slip Repair, Auckland

Project description

Drill 600mm diameter x 15m deep piles for slip repair

Machine used

Soilmec CM39

Special difficulties

Working off existing road to stabilize potential slip

Project Name - Chonny Crescent, Manukau

Project description

Drive 400mm square x 15m long precast concrete piles for under new silos

Machine used

PD6000

Special difficulties

Piles were installed to carry specific loadings.  These were tested using a PDA unit giving an instant report showing actual results

Project Name - Stormwater Pipeline, Auckland

Project description

Drill 20 x 18m deep piles and place universal columns and backfill with sand for top down construction of vertical access shaft for installing new stormwater pipeline

Machine used

CM39

Special difficulties

Traffic management and assisting with silt control was required.  Piling was a continuous operation as weak ground conditions posed a potential problem

Project Name - Transpower tower foundations

Project description

Install 12 x 1800mm diameter x 16m deep foundation with permanent caisson

Machine used

Soilmec R312

Project Name - Rosedale Outfall

Project description

Install 12m long sheet piles for 14m diameter access shaft

Machine used

Kobelco 55T crane with vibro hammer

Project Name - Bridge 51, Glen Eden Railway Station

Project description

Drilled piles at side of railway line for new pedestrian bridge

Machine used

Soilmec CM39

Special difficulties

Working in the rail corridor with consequent limited room and working hours

Project Name - Lift shaft at Great South Road, Manurewa

Project description

Drilling a lift shaft in concrete floor

Machine used

MTrack

Special difficulties

Commonly used in residential housing and light commercial buildings for drilling to install casings inside pile hole for lift shaft rams

Project Name - Kerikeri Bridge

Project description

Drilled and constructed 900mm diameter piles using permanent casings down to rock. Pier piles were in clusters of 10 with abutment piles each end

Machine used

R312

Project Name - Ormiston Road Bridge

Project description

Drilled 16 cast in situ piles x 750mm diameter x 13m deep and drove 98 350SED poles ranging from 4 – 8m in length

Machine used

Soilmec R312 and PD1200 pile driver